kitchen remodel #25
A few photos from the eighth day of the remodel. Plumbing rough-in is completed and electrical rough-in has started.
View from the stairs to the loft. The electrician had the plumber lower the vent stack so the outlets would fit under the window as planned. After this I made sure to review work plans on a daily basis instead of once every few days.

View to the stairs to the loft. The old track lighting is finally gone.

Electrical installed to the left of the second window.

Electrical installed to the right of the second window.

Electrical in the refrigerator/freezer nook.

Electrical and framing for the corner cabinet door from the dining room to the right of the range.

Electrical to the left of the range.

portlandpiper – Sat, 2008 – 08 – 23 13:35